Showing posts with label trellising. Show all posts
Showing posts with label trellising. Show all posts

Tuesday, 26 May 2009

Terry's Trellising


Ivan (left) and the team

The trellising is now nearing completion thanks to Mike Terry, Ivan and the team. It will have taken about ten days to install the 120 wooden end posts, 1,700 interim posts, 8,500 bamboo canes and more than 10,000 metres of wire to support the vines as they grow.

In spite of some difficult ragstone at the southern end of the vineyard, the work will be completed on time thanks to the tireless efforts of the guys in spite of the weather!

Next task is to mulch the vines which will hopefully keep the weeds at bay. The mulch will now comprise about 40 tonnes of green waste compost (20mm) mixed with 600 cu metres of wood chip (50mm).

Saturday, 2 May 2009

The Trellising Arrives from Germany

Philip Goddard on the forklift


Last Thursday the trellising arrived from Germany and is now safely stored in Philip Goddard's barn at Home Farm. For 5 acres of vines we need 140 timber end posts, around 1700 intermediate posts and a huge amount of wire.

Whilst we could wait a year after planting before erecting the trellising I have decided to get this out of the way early on and the job should be erected by the end of May.